← All measuresMeasures / Critical Raw Materials Act
Requirement · CPRM-07

Publish the permit-granting schedule drawn up by the single point of contact on the project's own free-access website.

Promoters of Strategic Projects must comply, and this is law in force.

Why it matters

This is law in force, not a proposal.

  • It is Art. 11(7), in the Critical Raw Materials Act. as of 2026-08-18
  • The act gives its timing as: From entry into force, 23 May 2024 (Art. 49(1)). as of 2026-08-18
  • It names 3 industries by name: Waste, Aluminium and Steel. as of 2026-08-18
  • Compliance is checked by none, per project. as of 2026-08-18
Addressee Promoters of Strategic ProjectsAct Regulation (EU) 2024/1252, consolidated 03.05.2024Article Art. 11(7)Class Businesses

The rule

New — no predecessor
Trigger

a detailed permitting schedule drawn up under Art. 11(7)

Obligation

Publish the permit-granting schedule drawn up by the single point of contact on the project's own free-access website.

Who is affected

Addressee
Promoters of Strategic Projects
Class
Businesses
Sectors
Names Waste and landfill, Aluminium and metals, Steel
Applies
From entry into force, 23 May 2024 (Art. 49(1))

Burden drivers

D1 — 1 of 7 marks fire on this provision.

Source text

Verbatim

The schedule shall be published by the project promoter on the website referred to in Article 8(5).

View source →