Simplification · CRMAB-PRM-09

Hold the permitting time limits where the project's nature, complexity, location or size requires longer -- six months more for extraction, three for processing or recycling.

Promoters of Strategic Projects must comply, and this is law in force.

Why it matters

This is law in force, not a proposal.

  • It is Art. 11(4), in the Critical Raw Materials Act. as of 2026-08-18
  • The act gives its timing as: From entry into force, 23 May 2024 (Art. 49(1)). as of 2026-08-18
  • It names 3 industries by name: Waste, Aluminium and Steel. as of 2026-08-18
  • Compliance is checked by competent authority, if it happens. as of 2026-08-18
Addressee Promoters of Strategic ProjectsAct Regulation (EU) 2024/1252, consolidated 03.05.2024Article Art. 11(4)Class Businesses

The rule

New — no predecessor
Trigger

an exceptional case turning on nature, complexity, location or size

Obligation

Hold the permitting time limits where the project's nature, complexity, location or size requires longer -- six months more for extraction, three for processing or recycling.

Who is affected

Addressee
Promoters of Strategic Projects
Class
Businesses
Sectors
Names Waste and landfill, Aluminium and metals, Steel
Applies
From entry into force, 23 May 2024 (Art. 49(1))

Burden drivers

No burden drivers recorded on this provision.

Source text

Verbatim

Member States may extend, before their expiry and on a case-by-case basis, the time limits referred to in: (a) paragraph 1, point (a), and paragraph 2, point (a), by a maximum of six months; (b) paragraph 1, point (b), and paragraph 2, point (b), by a maximum of three months.