← All measuresMeasures / Critical Raw Materials Act
Requirement · CSP-06

Report to the Commission every two years on implementation progress and permitting, on any slippage against the timetable and how it will be recovered, and on progress in financing including public support received.

Promoters of Strategic Projects must comply, and this is law in force.

Why it matters

This is law in force, not a proposal.

  • It is Art. 8(1), in the Critical Raw Materials Act. as of 2026-08-18
  • The act gives its timing as: Every two years from the date of recognition. as of 2026-08-18
  • It names 3 industries by name: Waste, Aluminium and Steel. as of 2026-08-18
  • Compliance is checked by none, every two years. as of 2026-08-18
Addressee Promoters of Strategic ProjectsAct Regulation (EU) 2024/1252, consolidated 03.05.2024Article Art. 8(1)Class Businesses

The rule

New — no predecessor
Trigger

recognition as a Strategic Project

Obligation

Report to the Commission every two years on implementation progress and permitting, on any slippage against the timetable and how it will be recovered, and on progress in financing including public support received.

Who is affected

Addressee
Promoters of Strategic Projects
Class
Businesses
Sectors
Names Waste and landfill, Aluminium and metals, Steel
Applies
Every two years from the date of recognition

Burden drivers

D1 · D5 — 2 of 7 marks fire on this provision.

Source text

Verbatim

The project promoter shall, every two years after the date of recognition as a Strategic Project, submit a report to the Commission containing information on at least: (a) progress in the implementation of the Strategic Project, in particular with regard to the permit-granting process; (b) where relevant, reasons for delays compared to the timetable referred to in Article 7(1), point (c) and a plan to overcome such delays; (c) progress in financing the Strategic Project, including information on public financial support.