Requirement · CSP-07Supply additional information on the project when the Commission asks for it to check that the recognition criteria are still met.
Promoters of Strategic Projects must comply, and this is law in force.
Why it matters
This is law in force, not a proposal.
- It is Art. 8(2), in the Critical Raw Materials Act. as of 2026-08-18
- The act gives its timing as: From entry into force, 23 May 2024 (Art. 49(1)). as of 2026-08-18
- It names 3 industries by name: Waste, Aluminium and Steel. as of 2026-08-18
- Compliance is checked by none, if it happens. as of 2026-08-18
The rule
New — no predecessor
Trigger
a Commission request for additional information
Obligation
Supply additional information on the project when the Commission asks for it to check that the recognition criteria are still met.
Who is affected
Addressee
Promoters of Strategic Projects
Class
Businesses
Sectors
Names Waste and landfill, Aluminium and metals, Steel
Applies
From entry into force, 23 May 2024 (Art. 49(1))
Burden drivers
D1 — 1 of 7 marks fire on this provision.
Source text
Verbatim
The Commission may, where necessary, request additional information from project promoters relevant to the implementation of the Strategic Project to ascertain the continuing fulfilment of the criteria laid down in Article 6(1).