← All measuresMeasures / Critical Raw Materials Act
Requirement · CSP-08

Notify the Commission of changes to the project that affect the recognition criteria, and of any lasting change of control over the undertakings involved.

Promoters of Strategic Projects must comply, and this is law in force.

Why it matters

This is law in force, not a proposal.

  • It is Art. 8(3), in the Critical Raw Materials Act. as of 2026-08-18
  • The act gives its timing as: From entry into force, 23 May 2024 (Art. 49(1)). as of 2026-08-18
  • It names 3 industries by name: Waste, Aluminium and Steel. as of 2026-08-18
  • Compliance is checked by none, if it happens. as of 2026-08-18
Addressee Promoters of Strategic ProjectsAct Regulation (EU) 2024/1252, consolidated 03.05.2024Article Art. 8(3)Class Businesses

The rule

New — no predecessor
Trigger

a change affecting the Art. 6(1) criteria or a lasting change of control

Obligation

Notify the Commission of changes to the project that affect the recognition criteria, and of any lasting change of control over the undertakings involved.

Who is affected

Addressee
Promoters of Strategic Projects
Class
Businesses
Sectors
Names Waste and landfill, Aluminium and metals, Steel
Applies
From entry into force, 23 May 2024 (Art. 49(1))

Burden drivers

D1 — 1 of 7 marks fire on this provision.

Source text

Verbatim

The project promoter shall notify the Commission of: (a) changes to the Strategic Project affecting its fulfilment of the criteria laid down in Article 6(1); (b) changes in control of the undertakings involved in the Strategic Project on a lasting basis, compared to the information referred to in Article 7(1), point (e).

View source →