Requirement · PRM-03Acknowledge completeness of a permit application, or request missing information, within a fixed deadline; a further deadline applies to a second request for missing information.
Member States' competent authorities must comply, and this is not law yet.
Why it matters
This is a Commission proposal: it is not law yet, and it can change before it is.
- It is Art. 5(3), in the Industrial Accelerator Act. as of 2026-08-17
- The act gives its timing as: Applies from [1 year after entry into force] per Art. 36. as of 2026-08-17
- It names no industry: it applies across the economy rather than to one of them. as of 2026-08-17
- Compliance is checked by competent authority, per application. as of 2026-08-17
The rule
New — no predecessor
Trigger
45 days from receipt of the application; second missing-information request within 30 days of receiving the previously requested information
Obligation
Acknowledge completeness of a permit application, or request missing information, within a fixed deadline; a further deadline applies to a second request for missing information.
Who is affected
Addressee
Member States' competent authorities
Class
Governments
Sectors
Reaches Steel, Cement and concrete, Aluminium and metals, Chemicals and refining, Automotive
Applies
Applies from [1 year after entry into force] per Art. 36
Burden drivers
D5 — 1 of 7 marks fire on this provision.
Source text
Verbatim
No later than 45 days from the receipt of the application for a permit for industrial manufacturing projects, the competent authority shall either acknowledge that the application is complete or request any missing information needed to process the application.