← All measuresMeasures / Net-Zero Industry Act
Requirement · NZIAB-INF-02

Publish every decision under the permitting section and Arts. 8, 15, 16 and 28 in an easily understandable form, with all decisions on one project on the same website.

Member States and their authorities must comply, and this is law in force.

Why it matters

This is law in force, not a proposal.

  • It is Art. 12(2), in the Net-Zero Industry Act. as of 2026-08-18
  • The act gives its timing as: Applies from 29 June 2024 (Art. 49(2)). as of 2026-08-18
  • It names 4 industries by name: Batteries and solar, Clean tech, Carbon capture and storage and Power. as of 2026-08-18
  • Compliance is checked by none, per decision. as of 2026-08-18
Addressee Member States and their authoritiesAct Regulation (EU) 2024/1735, consolidated 17.08.2025Article Art. 12(2)Class Governments

The rule

New — no predecessor
Trigger

any decision under the named provisions

Obligation

Publish every decision under the permitting section and Arts. 8, 15, 16 and 28 in an easily understandable form, with all decisions on one project on the same website.

Who is affected

Addressee
Member States and their authorities
Class
Governments
Sectors
Names Batteries and solar, Wind, heat pumps, hydrogen, Carbon capture and fuels, Power and heat
Applies
Applies from 29 June 2024 (Art. 49(2))

Burden drivers

D1 — 1 of 7 marks fire on this provision.

Source text

Verbatim

All decisions adopted pursuant to this Section and Articles 8, 15, 16 and 28 shall be made publicly available in an easily understandable manner

View source →