← All measuresMeasures / Net-Zero Industry Act
Requirement · NZIAB-SP-14Inform the promoter and hear it before repealing a recognition on grounds of substantial change, loss of the criteria, or incorrect information.
Member States and the Commission must comply, and this is law in force.
Why it matters
This is law in force, not a proposal.
- It is Art. 14(7), in the Net-Zero Industry Act. as of 2026-08-18
- The act gives its timing as: Applies from 29 June 2024 (Art. 49(2)). as of 2026-08-18
- It names 4 industries by name: Batteries and solar, Clean tech, Carbon capture and storage and Power. as of 2026-08-18
- Compliance is checked by none, if it happens. as of 2026-08-18
The rule
New — no predecessor
Trigger
a finding of substantial change, loss of criteria, or incorrect information
Obligation
Inform the promoter and hear it before repealing a recognition on grounds of substantial change, loss of the criteria, or incorrect information.
Who is affected
Addressee
Member States and the Commission
Class
Governments
Sectors
Names Batteries and solar, Wind, heat pumps, hydrogen, Carbon capture and fuels, Power and heat
Applies
Applies from 29 June 2024 (Art. 49(2))
Burden drivers
No burden drivers recorded on this provision.
Source text
Verbatim
it shall inform the project promoter concerned. After hearing the project promoter, the Member State may repeal the decision recognising a project as a net-zero strategic project.
View source →