← All measuresMeasures / Net-Zero Industry Act
Requirement · ENV-02Issue the reasoned conclusion on the environmental impact assessment within 90 days of receiving all necessary information and completing consultations.
Member State competent authorities must comply, and this is law in force.
Why it matters
This is law in force, not a proposal.
- It is Art. 10(3), in the Net-Zero Industry Act. as of 2026-08-18
- The act gives its timing as: Applies from 29 June 2024 (Art. 49(2)). as of 2026-08-18
- It names 4 industries by name: Batteries and solar, Clean tech, Carbon capture and storage and Power. as of 2026-08-18
- Compliance is checked by none, per project. as of 2026-08-18
The rule
New — no predecessor
Trigger
a completed environmental impact assessment for a net-zero technology manufacturing project
Obligation
Issue the reasoned conclusion on the environmental impact assessment within 90 days of receiving all necessary information and completing consultations.
Who is affected
Addressee
Member State competent authorities
Class
Governments
Sectors
Names Batteries and solar, Wind, heat pumps, hydrogen, Carbon capture and fuels, Power and heat
Applies
Applies from 29 June 2024 (Art. 49(2))
Burden drivers
D5 — 1 of 7 marks fire on this provision.
Source text
Verbatim
Member States shall ensure that the competent authorities issue the reasoned conclusion referred to in Article 1(2), point (g)(iv), of Directive 2011/92/EU on the environmental impact assessment within 90 days of receiving all necessary information pursuant to Articles 5, 6 and 7 of that Directive and after completing the consultations referred to in Articles 6 and 7 of that Directive.