Requirement · SPC-01

Establish or designate one or more single points of contact responsible for facilitating and coordinating the permit-granting process for net-zero technology manufacturing projects.

Member States must comply, and this is law in force.

Why it matters

This is law in force, not a proposal.

  • It is Art. 6(1), in the Net-Zero Industry Act. as of 2026-08-18
  • The act gives its timing as: By 30 December 2024. as of 2026-08-18
  • It names 4 industries by name: Batteries and solar, Clean tech, Carbon capture and storage and Power. as of 2026-08-18
  • Compliance is checked by none, one-off. as of 2026-08-18
Addressee Member StatesAct Regulation (EU) 2024/1735, consolidated 17.08.2025Article Art. 6(1)Class Governments

The rule

New — no predecessor
Trigger

entry into application of the Regulation

Obligation

Establish or designate one or more single points of contact responsible for facilitating and coordinating the permit-granting process for net-zero technology manufacturing projects.

Who is affected

Addressee
Member States
Class
Governments
Sectors
Names Batteries and solar, Wind, heat pumps, hydrogen, Carbon capture and fuels, Power and heat
Applies
By 30 December 2024

Burden drivers

D4 — 1 of 7 marks fire on this provision.

Source text

Verbatim

By 30 December 2024 Member States shall establish or designate one or more authorities as single points of contact at the relevant administrative level. Each single point of contact shall be responsible for facilitating and coordinating the permit-granting process for net-zero technology manufacturing projects, including for net-zero strategic projects, and for providing information on streamlining the administrative processes in accordance with Article 7, including information on when an application is considered to be completed in accordance with Article 9(10).