← All measuresMeasures / Net-Zero Industry Act
Entitlement · PRM-04

A decarbonisation project spanning several facilities on one site may be split, by agreement with the single point of contact, into smaller projects so each fits the permitting time limits.

Promoters of energy-intensive industry decarbonisation projects are given a right, and this is law in force.

Why it matters

This is law in force, not a proposal.

  • It is Art. 9(3), in the Net-Zero Industry Act. as of 2026-08-18
  • The act gives its timing as: Applies from 29 June 2024 (Art. 49(2)). as of 2026-08-18
  • It names 5 industries by name: Steel, Aluminium, Chemicals, Cement and Glass. as of 2026-08-18
  • Compliance is checked by competent authority, per project. as of 2026-08-18
Addressee Promoters of energy-intensive industry decarbonisation projectsAct Regulation (EU) 2024/1735, consolidated 17.08.2025Article Art. 9(3)Class Businesses

The rule

New — no predecessor
Trigger

the project requires the construction of several facilities or units on one site

Entitlement

A decarbonisation project spanning several facilities on one site may be split, by agreement with the single point of contact, into smaller projects so each fits the permitting time limits.

Who is affected

Addressee
Promoters of energy-intensive industry decarbonisation projects
Class
Businesses
Sectors
Names Steel, Aluminium and metals, Chemicals and refining, Cement and concrete, Glass and ceramics
Applies
Applies from 29 June 2024 (Art. 49(2))

Burden drivers

No burden drivers recorded on this provision.

Source text

Verbatim

Where energy-intensive industry decarbonisation projects, including when recognised as strategic projects, require the construction of several facilities or units in one site, the project promoter and the single point of contact may agree on splitting the project into several smaller projects for the purposes of complying with the applicable time limits.