Requirement · PRM-01

Complete the permit-granting process for a net-zero technology manufacturing project within 12 months below 1 GW of yearly manufacturing capacity, or 18 months at 1 GW or more.

Member State permit-granting authorities and single points of contact must comply, and this is law in force.

Why it matters

This is law in force, not a proposal.

  • It is Art. 9(1), in the Net-Zero Industry Act. as of 2026-08-18
  • The act gives its timing as: Applies from 29 June 2024 (Art. 49(2)). as of 2026-08-18
  • It names 4 industries by name: Batteries and solar, Clean tech, Carbon capture and storage and Power. as of 2026-08-18
  • Compliance is checked by none, per application. as of 2026-08-18
Addressee Member State permit-granting authorities and single points of contactAct Regulation (EU) 2024/1735, consolidated 17.08.2025Article Art. 9(1)Class Governments

The rule

New — no predecessor
Trigger

a permit-granting application for a net-zero technology manufacturing project

Obligation

Complete the permit-granting process for a net-zero technology manufacturing project within 12 months below 1 GW of yearly manufacturing capacity, or 18 months at 1 GW or more.

Who is affected

Addressee
Member State permit-granting authorities and single points of contact
Class
Governments
Sectors
Names Batteries and solar, Wind, heat pumps, hydrogen, Carbon capture and fuels, Power and heat
Applies
Applies from 29 June 2024 (Art. 49(2))

Burden drivers

D5 — 1 of 7 marks fire on this provision.

Source text

Verbatim

The permit-granting process for net-zero technology manufacturing projects shall not exceed any of the following time limits: (a) 12 months for the construction or expansion of net-zero technology manufacturing projects with a yearly manufacturing capacity of less than 1 GW; (b) 18 months for the construction or expansion of net-zero technology manufacturing projects with a yearly manufacturing capacity of 1 GW or more.

View source →