← All measuresMeasures / Net-Zero Industry Act
Requirement · PRM-03

Draw up a detailed schedule for the permit-granting process within two months of the application and publish it on a free-access website.

Single points of contact must comply, and this is law in force.

Why it matters

This is law in force, not a proposal.

  • It is Art. 9(11), in the Net-Zero Industry Act. as of 2026-08-18
  • The act gives its timing as: Applies from 29 June 2024 (Art. 49(2)). as of 2026-08-18
  • It names 4 industries by name: Batteries and solar, Clean tech, Carbon capture and storage and Power. as of 2026-08-18
  • Compliance is checked by none, per application. as of 2026-08-18
Addressee Single points of contactAct Regulation (EU) 2024/1735, consolidated 17.08.2025Article Art. 9(11)Class Governments

The rule

New — no predecessor
Trigger

receipt of a permit-granting application

Obligation

Draw up a detailed schedule for the permit-granting process within two months of the application and publish it on a free-access website.

Who is affected

Addressee
Single points of contact
Class
Governments
Sectors
Names Batteries and solar, Wind, heat pumps, hydrogen, Carbon capture and fuels, Power and heat
Applies
Applies from 29 June 2024 (Art. 49(2))

Burden drivers

D1 · D5 — 2 of 7 marks fire on this provision.

Source text

Verbatim

No later than two months from the date of the receipt of the application, the single point of contact shall draw up, in close cooperation with other authorities concerned, a detailed schedule for the permit-granting process. That schedule shall start from the moment when the single point of contact acknowledges the completeness of the application. The schedule shall be published by the single point of contact on a free access website.