Requirement · PRM-02

Acknowledge that a permit application is complete, or state exactly what is missing, within 45 days; a second request for information may be made within 30 days and may not open new subjects.

Single points of contact must comply, and this is law in force.

Why it matters

This is law in force, not a proposal.

  • It is Art. 9(10), in the Net-Zero Industry Act. as of 2026-08-18
  • The act gives its timing as: Applies from 29 June 2024 (Art. 49(2)). as of 2026-08-18
  • It names 4 industries by name: Batteries and solar, Clean tech, Carbon capture and storage and Power. as of 2026-08-18
  • Compliance is checked by none, per application. as of 2026-08-18
Addressee Single points of contactAct Regulation (EU) 2024/1735, consolidated 17.08.2025Article Art. 9(10)Class Governments

The rule

New — no predecessor
Trigger

receipt of a permit-granting application

Obligation

Acknowledge that a permit application is complete, or state exactly what is missing, within 45 days; a second request for information may be made within 30 days and may not open new subjects.

Who is affected

Addressee
Single points of contact
Class
Governments
Sectors
Names Batteries and solar, Wind, heat pumps, hydrogen, Carbon capture and fuels, Power and heat
Applies
Applies from 29 June 2024 (Art. 49(2))

Burden drivers

D5 — 1 of 7 marks fire on this provision.

Source text

Verbatim

No later than 45 days from the receipt of the permit-granting application, the single point of contact concerned shall acknowledge that the application is complete or, if the project promoter has not sent all the information required to process the application, request the project promoter to submit a complete application without undue delay, specifying which information is missing. In the event that the submitted application is deemed to be incomplete for a second time, the single point of contact may, within 30 days of the second submission, make a second request for information. The single point of contact shall not request information in areas not covered in the first request for additional information and shall be entitled only to request further evidence to complete the identified missing information. The date of the acknowledgement of the completeness of the application from the single point of contact referred to in Article 6(1) shall serve as the start of the permit-granting process for that particular application.