← All measuresMeasures / Net-Zero Industry Act
Requirement · SPC-04Specify and hand to the single point of contact the requirements and the extent of the information that will be demanded of a project promoter, before the permit-granting process starts.
Authorities involved in the permit-granting process must comply, and this is law in force.
Why it matters
This is law in force, not a proposal.
- It is Art. 6(9), in the Net-Zero Industry Act. as of 2026-08-18
- The act gives its timing as: Applies from 29 June 2024 (Art. 49(2)). as of 2026-08-18
- It names 4 industries by name: Batteries and solar, Clean tech, Carbon capture and storage and Power. as of 2026-08-18
- Compliance is checked by none, recurring. as of 2026-08-18
The rule
New — no predecessor
Trigger
a permit-granting process for a net-zero technology manufacturing project
Obligation
Specify and hand to the single point of contact the requirements and the extent of the information that will be demanded of a project promoter, before the permit-granting process starts.
Who is affected
Addressee
Authorities involved in the permit-granting process
Class
Governments
Sectors
Names Batteries and solar, Wind, heat pumps, hydrogen, Carbon capture and fuels, Power and heat
Applies
Applies from 29 June 2024 (Art. 49(2))
Burden drivers
No burden drivers recorded on this provision.
Source text
Verbatim
The authorities involved in the permit-granting process and other authorities concerned shall specify and make available to the single point of contact concerned, the requirements and extent of information requested of a project promoter before the permit-granting process commences.
View source →