Simplification · SPC-03Re-run studies or re-obtain permits and authorisations already carried out or issued for the same project.
Promoters of net-zero technology manufacturing projects must comply, and this is law in force.
Why it matters
This is law in force, not a proposal.
- It is Art. 6(5), in the Net-Zero Industry Act. as of 2026-08-18
- The act gives its timing as: Applies from 29 June 2024 (Art. 49(2)). as of 2026-08-18
- It names 4 industries by name: Batteries and solar, Clean tech, Carbon capture and storage and Power. as of 2026-08-18
- Compliance is checked by competent authority, per application. as of 2026-08-18
The rule
New — no predecessor
Trigger
a study, permit or authorisation already exists for the project
Obligation
Re-run studies or re-obtain permits and authorisations already carried out or issued for the same project.
Who is affected
Addressee
Promoters of net-zero technology manufacturing projects
Class
Businesses
Sectors
Names Batteries and solar, Wind, heat pumps, hydrogen, Carbon capture and fuels, Power and heat
Applies
Applies from 29 June 2024 (Art. 49(2))
Burden drivers
No burden drivers recorded on this provision.
Source text
Verbatim
The competent authorities shall ensure that any relevant studies carried out, or permits or authorisations issued, for a given project are taken into account and that no duplicate studies, permits or authorisations are required, unless otherwise required under Union or national law.