← All measuresMeasures / Net-Zero Industry Act
Entitlement withdrawn · SP-06Strategic-project status, and every right attached to it, is lost where the project changes substantially, stops meeting the criteria, or was recognised on incorrect information.
Promoters of net-zero strategic projects are given a right, and this is law in force.
Why it matters
This is law in force, not a proposal.
- It is Art. 14(8), in the Net-Zero Industry Act. as of 2026-08-18
- The act gives its timing as: Applies from 29 June 2024 (Art. 49(2)). as of 2026-08-18
- It names 4 industries by name: Batteries and solar, Clean tech, Carbon capture and storage and Power. as of 2026-08-18
- Compliance is checked by competent authority, if it happens. as of 2026-08-18
The rule
New — no predecessor
Trigger
substantial change, loss of the Art. 13 criteria, or recognition based on incorrect information
Entitlement
Strategic-project status, and every right attached to it, is lost where the project changes substantially, stops meeting the criteria, or was recognised on incorrect information.
Who is affected
Addressee
Promoters of net-zero strategic projects
Class
Businesses
Sectors
Names Batteries and solar, Wind, heat pumps, hydrogen, Carbon capture and fuels, Power and heat
Applies
Applies from 29 June 2024 (Art. 49(2))
Burden drivers
No burden drivers recorded on this provision.
Source text
Verbatim
A project which is no longer recognised as a net-zero strategic project shall lose all rights connected to that status under this Regulation.